Assigned to a bridge construction project with pile driving within the river. Must contain silt during pile driving operations or be shutdown due to fish breeding season. Any suggestions. Average depth is 6-8 feet in most locations, but very fast moving.
cvg (Civil/Environme)
23 Mar 04 15:55
Thread274-64105
Check out this thread in the Geotechnical Engineers / Earth retention engineering forum. The recommended a sort of water filled geotextile tube / cofferdam which could be placed around your pile driver to help contain the silt.